Ateneum Art Museum
Senaatti-kiinteistöt

Ateneum's permanent art collections and changing exhibitions set the indoor climate with very specific requirements. Among the works of art of the Picasso exhibition, the Finnish state guaranteed EUR 1.3 billion. Part of the guarantee was signed with the assurance that the conditions will remain within the required limits.

Hepacon responded to the customer's promise with the building automation design solutions. The solution included building temperature, humidity, lighting, air quality and pressure relations management. The design started in 2009 and the project with a surface of 17600 m2 was completed in 2012.

In addition, Hepacon has drawn up a ten-year long-term plan and an explosion protection document.